The Motley is quickly taking shape in Nashville’s Midtown neighborhood. The 516,000-square-foot development will include over 325 residential units in the 27-story tower.
Charter celebrated topping out the project in September 2026 after providing turnkey structural concrete services—including all labor and materials for formwork, reinforcing, and concrete.
Bringing the Site Into Focus
For Charter Project Manager Alex Nance, the project has been a reminder that some of the most important decisions happen before a structure ever starts rising.
Prior to beginning foundations, mass excavation work revealed inconsistent rock elevations, which affected the design of the closure system. Charter used 3-D scanning technology to capture the conditions in the excavation and help determine exactly where additional closure walls were needed.
“Once the mass excavation was complete, we were able to 3-D scan the hole and drop our model into that,” Alex said. “That showed us exactly how much space we had to work with.”
The information ultimately led to a revised approach that extended the closure walls farther into the excavation. Additional closure walls required the team to rethink portions of the below-grade sequence, including how the post-tensioning work would be performed.
Adapting as the Work Takes Shape
With the revised approach in place, Charter worked closely with the general contractor and project partners to incorporate the changes. Because Charter owns and manages its own formwork, the team was able to begin revising formwork details and sequencing immediately. One of the solutions was a hybrid approach that combined one-sided and two-sided walls, allowing the team to construct the closure walls within the existing excavation without having to re-excavate portions of the site.
The team also adjusted its pour sequence, breaking some larger pours into smaller sections where necessary while maintaining the overall construction sequence as much as possible.
“There were a lot of moving pieces in a short amount of time,” Alex said. “We were collaborating on fixes and ideas and working together to get those pieces in place.”
That adaptability has been especially important during the project’s demanding early stages. The team worked six days a week through much of the below-grade and early vertical construction, with a peak field crew of approximately 90 people.
Built to be a Partner
The Motley required the kind of coordination and problem-solving that comes with working on a complex project, bringing Charter’s field experience, technology, and collaborative approach into play.
“We don’t want to be the kind of partner that says, ‘That’s someone else’s problem,” Alex said. “We want to be proactive.”
At The Motley, that mindset meant using better information to understand the conditions, helping develop a workable solution, and leaning in to keep the project moving in order to build another historic project in the heart of Nashville.